Week of October 2 :
- Paving is complete on Douglas Avenue
- All major concrete work will be completed this week. Minor clean-up and detail work will be accomplished the week of October 9th.
- Wire for the new antique street lights has been installed in the conduits and the light will be erected during the week of October 15th.
- New City Hall Clock has been ordered and installed in December.
- Douglas Avenue pavement profiling and preparation for paving will be done on October 11th thru 13th. Street closures will occur at this time.
- Paving is scheduled for completion during the week of October 23rd.