PROJECT UPDATES:
Week of October 30 :
- Paving is complete on Douglas Avenue
- Masonry work for the stone planters and inlayed sidewalk areas will begin, Tuesday, Oct. 31.
- The stamped and textured pedestrian crosswalks will be installed
this week, weather permitting
- All streetlights have been installed and will be operational in two weeks